PRELIMINARY TIMELINE
MCSD CAPTIAL PROJECT PRELIMINARY TIMELINE
Referendum Vote May 2019
Design Phase June-December 2019
SED Review & Approval * January-August 2020
Public Bid & BOE Award Fall 2020
Construction Spring 2021-2022
Note: SED review times are unpredictable. Currently Mechanical reviews are taking 38-40 weeks and Architectural Reviews are taking 2-4 weeks
Board of Education Meetings
Board of Education meeting 8/16/18
- Presentation by Beth Ferguson, Vice President, Financial Advisor from Capital Markets Advisors on finances
- Review pre-referendum and project timeline
- Construction Manager Request for Proposal
Board of Education meeting 9/20/18
- Present preliminary Capital Project Scoping Document
- Appoint Citizen’s Advisory Committee
Board of Education meeting 10/18/18
- Capital Project update
- Appoint Construction Manager for Project
Board of Education meeting 11/15/18
- Capital Project update
- Start State Environmental Quality Review Act (SEQRA) process
Community Forum/QA Session TBD
Board of Education meeting 12/20/18
- Finalize Capital Project Scope and Budget
Board of Education meeting 1/17/19
- Communications Planning
Board of Education meeting 2/28/19
- SEQRA Resolution
- Proposition Resolution for May 2019 Voter Referendum
Community Information Sessions 11/10/18-5/18/19
Community Vote 5/21/19